    Release Date:
  
  
    Wednesday, 3 June 2015 - 2:00pm  
The Ministry of Finance and the Project Support Service Unit are advising residents of the Carrot Bay community and surrounding areas that work on the Carrot Bay Jetty is progressing. Construction work began on May 21 and is expected to last for a period of five months. On completion, the L shaped dock will be approximately 100 feet on the long axis, 40 feet on the short axis, and eight feet wide.
The Ministry of Finance and the Project Support Service Unit apologises for any inconvenience caused as a result of the construction of the new Carrot Bay Jetty.